Cycle Time is a measure of how lengthy it takes to get a brand new characteristic in a
software program system from thought to working in manufacturing. In Agile circles, we attempt
to reduce cycle time. We do that by defining and implementing very small
options and minimizing delays within the growth course of. Though the tough
notion of cycle time, and the significance of decreasing it, is frequent, there’s a
lot of variations on how cycle time is measured.
A key attribute of agile software program growth is a shift from a
Waterfall Course of, the place work is decomposed primarily based on
exercise (evaluation, coding, testing) to an Iterative Course of the place work is
primarily based on a subset of performance (easy pricing, bulk low cost,
valued-customer low cost). Doing this generates a suggestions loop the place we will be taught
from placing small options in entrance of customers. This studying permits us to
enhance our growth course of and permits us to higher perceive the place the
software program product can present worth for our clients.
This suggestions is a core good thing about an iterative method, and like most
such suggestions loops, the faster I get the suggestions, the happier I’m. Thus
agile people put plenty of emphasis on how briskly we will get a characteristic by way of the
complete workflow and into manufacturing. The phrase cycle time is a measure of that.
However right here we run into difficulties. When can we begin and cease the clock on
cycle time?
The stopping time is the simplest, most glibly it is when the characteristic is put
into manufacturing and serving to its customers. However there are circumstances the place this
can get muddy. If a crew is utilizing a Canary Launch, ought to it
be when utilized by the primary cohort, or solely when launched to the total
inhabitants? Will we depend solely when the app retailer has permitted its launch, thus
including an unpredictable delay that is principally outdoors the management of the
growth crew?.
The beginning time has much more variations. A standard marker is when a
developer makes a primary decide to that characteristic, however that ignores any time
spent in preparatory evaluation. Many individuals would go additional again and say:
“when the shopper first has the thought for a characteristic”. That is all very nicely
for a excessive precedence characteristic, however how about one thing that is not that pressing,
and thus sits in a triage space for a number of weeks earlier than being able to enter
growth. Will we begin the clock when the crew first locations the characteristic on
the cardboard wall
and we begin to severely work on it?
I additionally run into the section lead time, generally as an alternative of
“cycle time”, however typically collectively – the place folks make a distinction between the
two, typically primarily based on a unique begin time. Nevertheless there’s no
consistency between how folks distinguish between them. So generally, I
deal with “lead time” as a synonym to “cycle time”, and if somebody is utilizing each,
I ensure that I perceive how that particular person is making the excellence.
The completely different bands of cycle time all have their benefits, and it is typically
helpful to make use of completely different bands in the identical scenario, to spotlight variations.
In that scenario, I would use a distinguishing adjective (e.g. “first-commit cycle
time” vs “thought cycle time”) to inform them aside. There is not any usually accepted
phrases for such adjectives, however I believe they’re higher than making an attempt to
create a distinction between “cycle time” and “lead time”.
What these questions inform us is that cycle time, whereas a helpful idea, is
inherently slippery. We must be cautious of evaluating cycle instances between groups,
except we may be assured now we have constant notions of their cease and begin instances.
However regardless of this, considering by way of cycle time, and making an attempt to reduce
it, is a helpful exercise. It is normally worthwhile to construct a price stream map
that reveals each step from thought to manufacturing, figuring out the steps within the
work stream, how a lot time is spent on them, and the way a lot ready between them.
Understanding this stream of labor permits us to seek out methods to scale back the cycle
time. Two generally efficient interventions are to scale back the dimensions of options
and (counter-intuitively) improve Slack. Doing the work to
perceive stream to enhance it’s worthwhile as a result of
the quicker we get concepts into manufacturing, the extra
quickly we acquire the advantages of the brand new options, and get the suggestions to
be taught and enhance our methods of working.